Trail Improvement Project – Atlanta South

One of our trail improvement projects for 2023 was to shore up several slopes on the snowmobile trail south of Atlanta. We had local contractor Team Elmers deliver 26 tons of aggregate to a location near the trail which we then hauled and spread on the trail.

The first of the photos shows a “before” section on the trail that had a rain-rut develop even though stone had been in place on the slope for a number of years. Of course it would have been much worse had that stone not been there. The project included filling in that rut, adding more stone and shaping that slope and a couple others nearby.

Snowmobile Trail funds were used to support this project on State Land.

Comments are closed.